The Kalamazoo Resort has come a long way in our expansion project over the last year, and we’re close to completion! We have made a ton of progress, despite major delays at the start of 2021 due to COVID-19. Check out what we’ve been up to below.
November 2021
- The existing sewer main was revamped and the new sewer was dug into the sites.
December 2021
- Water was dug in and installed at every site along with the electrical.
- All of the water spigots were installed along with the sewer hookups at every site.
January 2022
- The site storm drainage was installed along with the storm catch basins.
- We are continuing to grade surrounding areas as weather permits.
Stay updated and follow along on our progress by continuing to visit the website. If you have a specific question or concern, please call us at 989-671-1125 and select option 1 for Member Services or email us at info@outdooradventuresinc.com. We hope you’re as excited about the completion of this project as we are!
0 Comment